August 28, 2023 at 9:26 am #5157
FABRIC Users,
Due to a power outage affecting the FABRIC Dataplane Services infrastructure, all dataplane for new slices are affected. No new dataplane connection can be created at the moment. Traffic for existing slices should be working fineĀ Hence its safer to assume all FABRIC dataplane is affected. No known ETA is available. Users will be informed once the issue has been resolved.
August 29, 2023 at 10:08 am #5169This outage has been resolved.
August 29, 2023 at 11:08 am #5177Still website is giving error like :
“Notice: Due to a major power outage in the area, some FABRIC services including the dataplane are currently unavailable.”
Apart from that, these 2 network componenets are still “ticketed” for 10 minutes :
7220acbd-e677-43d1-a0d6-282fcbc6ca12 net_s1_s2 network Ticketed 65a44115-4a68-44e8-b445-00b75623b73f net_s2_s3 network Ticketed Is it related to the outage?
Kind regards,
Nagmat
August 29, 2023 at 11:53 am #5178Still website is giving error like :
“Notice: Due to a major power outage in the area, some FABRIC services including the dataplane are currently unavailable.”
Apart from that, these 2 network componenets are still “ticketed” for 10 minutes :
7220acbd-e677-43d1-a0d6-282fcbc6ca12 net_s1_s2 network Ticketed 65a44115-4a68-44e8-b445-00b75623b73f net_s2_s3 network Ticketed Is it related to the outage?
Kind regards,
Nagmat
The error is :
failed lease update- all units failed priming: Exception during create for unit: 7220acbd-e677-43d1-a0d6-282fcbc6ca12 Playbook has failed tasks: NSO commit returned JSON-RPC error: type: rpc.method.failed, code: -32000, message: Method failed, data: message: External error in the NED implementation for device dall-data-sw: Tue Aug 29 14:55:57.056 UTCrnrn Failed to commit one or more configuration items during a pseudo-atomic operation. All changes made have been reverted.rn SEMANTIC ERRORS: This configuration was rejected by rn the system due to semantic errors. The individual rn errors with each failed configuration command can be rn found below.rnrnrnl2vpnrn bridge group bg-net_s1_s2-7220acbd-e677-43d1rn bridge-domain bd-net_s1_s2-7220acbd-e677-rn interface HundredGigE0/0/0/9.2056rn Invalid argument: Interface already used for L2VPNrn rn rn rnrnend, internal: jsonrpc_tx_commit357#all units failed priming: Exception during create for unit: 7220acbd-e677-43d1-a0d6-282fcbc6ca12 Playbook has failed tasks: NSO commit returned JSON-RPC error: type: rpc.method.failed, code: -32000, message: Method failed, data: message: External error in the NED implementation for device dall-data-sw: Tue Aug 29 14:55:57.056 UTCrnrn Failed to commit one or more configuration items during a pseudo-atomic operation. All changes made have been reverted.rn SEMANTIC ERRORS: This configuration was rejected by rn the system due to semantic errors. The individual rn errors with each failed configuration command can be rn found below.rnrnrnl2vpnrn bridge group bg-net_s1_s2-7220acbd-e677-43d1rn bridge-domain bd-net_s1_s2-7220acbd-e677-rn interface HundredGigE0/0/0/9.2056rn Invalid argument: Interface already used for L2VPNrn rn rn rnrnend, internal: jsonrpc_tx_commit357#
August 29, 2023 at 3:37 pm #5181What you observed was part of the consequences of the outage. We believe most of them have been by now cleaned up (including UCSD and DALL) however the banner remains on the portal because we are still testing.
-